You can manage the procurement process using the Procurement control tool. The tool is linked with the Advance Bill module in Tekla PowerFab.
The tool utilizes procurement numbering that adds a preliminary number to parts that will be used by Tekla Structures and Tekla PowerFab. The number is used for tracking the progress of parts in the procurement workflow.
This numbering system does not allow setting start numbers, which are determined by the order of submittals instead. For each submittal to the fabricator, the numbering starts from the highest last submitted number.
The Procurement control dialog works in the same way as numbering preview.
For more information on numbering preview, see Preview the numbering results.
Template properties
The values of the procurement per parts can be used in reports or in filtering by template attributes.
| Property | Description |
|---|---|
| PROCUREMENT_STATUS | Status of procurement
|
| PROCUREMENT_POSITION | Full mark of the procured part, including prefix |
| PROCUREMENT_NUMBER | Only the number of the procured parts |
| PROCURED_PROFILE | The profile value from the last submittal of the part |
| PROCURED_MATERIAL | The material value from the last submittal of the part |
| PROCURED_LENGTH | The LENGTH_NET value from the last submittal of the part |
When a part is excluded, it is not taken into account in the workflow at all, nor is it included in the Tekla PowerFab Advance Bill module. If you only want to submit a certain phase of the project, you should not exclude the parts in other phases but only select the parts in the specific phase and number them.
When you have submitted a part and want to undo the submittal, you can exclude the part and submit. The excluded part is now submitted to the fabricator as a “deleted part”. This means that the part is deleted from the procurement workflow.
Procurement control settings
You can define settings that affect procurement numbering and tolerances for change detection. in the Procurement control settings dialog.
If Use fabricator settings is used, the values in the Procurement control settings are overwritten with the preferred values from your selected fabricator.
For procurement numbering, parts are grouped by three parameters:
- net length
- profile
- material
For example, when the beam net length tolerance is 200 mm, the beam length is in length groups 0–199.99, 200–399.99, 400–599.99, etc.
After a part is submitted with a procurement number to the fabricator, the integrated change detection informs the detailer if the part has been significantly changed from the original procurement.
The change detected in the length of a procured part depends on the tolerances. There are different tolerances for extending and shortening of the length.

.
. (Optional)
.
. See Procurement
control settings below.