Change the Elevation of an Existing Spot

  1. Open a job in the Manage Earthwork Estimates screen.
    Remarque : To open a job in the Manage Earthwork Estimates screen, click Estimating > Earthwork > Manage Earthwork Estimates in the All Tasks pane. Click Open Existing Job. Then select the job you want to open, and click OK.
  2. Select the Takeoff tab, if it is not already active.
  3. In the Active Layer field on the toolbar, click to select the layer for which you want to change the spot elevations.
  4. Click Select on the speedbar.
  5. Select the spot elevation you want to change.
  6. Click Prop on the speedbar.
  7. In the Elevation field, enter the new spot elevation.
  8. Cliquez sur OK.