JC Open Job Estimates Drilldown
You can use the JC Open Job Estimates Drilldown report by selecting
.The JC Open Job Estimates Drilldown prints jobs with a status of "1" Open only.
Selections at runtime include Job range and the options to include job master information and estimates on the first level.
(Level 2) shows original estimated costs and current estimates.
The Cost Type level (Level 3) includes current estimated hours, units and cost. The units at this last level are reported in three different columns. Estimated Units for the Cost Type, Item Units. Only units where the Item flag is checked in JC Original Estimates, and Phase Units. Only units where the Phase Unit flag is checked in JC Original Estimates.
Access this report by clicking Job Cost > Reports > JC Open Job Estimates Drilldown.
Report Parameters |
Description |
---|---|
Company |
Accept the default, or press F4 to select a company. |
Beginning Job |
Select the Field Lookup button or press F4 to select the beginning job. |
Ending Job |
Select the Field Lookup button or press F4 to select the ending job. |
Show Estimate Information at Job Level |
checkbox to show estimate information at the job level. |
Print Job Information |
checkbox to print job information |