Charge a Time + Material Change Order to a Fixed Job

If you need to record a T+ M change order to a fixed price job, complete the following steps. The follow procedure assumes that you are creating additional phase to track this T+ M activity.

  • On the Site Map, click Job Cost > Maintenance > Phases.

  • Enter a Job code.

  • Click the New button.

  • Complete the fields in the New Phase window. In the Price type field, select 'Time + Material'.

  • Click OK until you return to the Site Map screen.

  • Click Time + Material > Maintenance > Job Billing Setup.

  • Enter a Job and Customer code, and then complete the relevant fields in the Properties and Billing details, and Billing address sections.

  • Enter any Mark-ups, Add-ons, and Fees for this job.

  • Click Save to return to the Site Map.

The following steps are optional. Complete them only if you want to record that there were estimates and a change order.

  • On the Site Map screen, click Accounts Receivable > Data Entry Change Order Entry.

  • Complete the Job, Customer, Change order, and Current status fields.

  • Add a change request to the newly created phase using the detail portion of the screen.

  • Click Save to return to the Site Map.