Job Cost Analysis Report
You can preview the Job Cost Analysis Report with or without projected costs. This data comes from the Job Analysis Inquiry screen. The information for each job displays in sequence by phase code.
If the Include open commitments and Include A/P invoices in progress checkboxes are selected in the Job Cost Installation - Report Defaults screen, subcontract invoice amounts will be omitted.
If subcontract billings are routed through the approval process, then this report should be run with the Include open commitments checkbox clear. This will show the unapproved subcontract billings in the job-to-date costs, and the open commitments will display in a separate column on the report.