Report Calculations - Job Summary Cost Report (Projected Cost = Yes)
The following table describes how each column is calculated on this report.
Field |
Description |
---|---|
Job To Date |
Actual job-to-date costs through the designated year and period display. |
Projected |
The total cost projected at completion displays from Job Phases. |
Estimate |
The current estimated amount displays from Job Phases. |
Standard Format |
Figures in the labor, materials, and subcontract columns are for the corresponding cost types for each phase (the labor and subcontract columns contains cost types designated on the start screen; all other cost types are contained in the materials column). The totals columns provide the sums of figures in the three cost-type columns. |
Expanded Format |
Figures in the labor, material, subcontract, cost type #4 and cost type #5 columns are for the corresponding cost types for each phase. The labor, subcontract, cost type #4 and cost type #5 columns contain the cost type(s) specified on the starting screen for this report. All other cost types are contained in the materials column. The totals columns provide the sums of figures in the five cost type columns. |