Deactivate or Activate a Project Package

You can deactivate a project package if it is no longer needed, and reactivate it if needed.

Packages are deactivated instead of deleted so they are still included in statistical analysis and reports.
  1. Select the menu icon in the upper left corner, then choose Project Setup. Select Project Packages.
  2. To deactivate a package:
    1. Select the checkbox next to the package you want to deactivate and select Deactivate in the upper right corner. Use the search field to make finding the packages easier.
    2. Select Yes to confirm the deactivation.
  3. To reactive a package:
    1. Select Filter from the upper left corner.
    2. Choose Show Inactive Packages.
    3. Select the Show Inactive Packages checkbox. The Project Packages page displays the deactivated packages.
    4. Choose the checkboxes of the packages to make active. Use the Search field to make finding the packages easier.
    5. Select Activate in the upper right corner.
    6. Repeat the steps to clear the Show Inactive Packagescheckbox.
Packages are deactivated or activated.