About the PM PCO Items Create SubCOs Form
Use this form to create subcontract change orders (SCOs) using PCO detail items. It can be accessed by selecting on the PM Pending Change Orders form.
The following must be true to create SubCOs from PCO detail items:
- There must be a subcontract and subcontract line item associated with a PCO detail item - PCO detail items are entered using the Estimate/Purchase Details tab on PM Pending Change Orders, and they are associated with a subcontract and subcontract item using the SL and PO/SL Items fields
- The subcontract item cannot already be associated with an SubCO- each subcontract item can only be associated with one SubCO
- The subcontract associated with the PCO detail item must be approved, or interfaced- subcontracts are approved using the Approvedcheckbox on the Info tab of PM Subcontracts and they are interfaced using PM Interface
Key Features
This form has the following key features:
- You can create one or many SubCOs - A separate SubCO will be created for each PCO detail item associated with a unique subcontract. This is because an SubCO can only be associated with a single subcontract. PCO detail items associated with the same subcontract will be grouped together onto a single SCO.
- You can add items to an existing SubCO - If all of the PCO detail items are associated with the same subcontract, you can add these items to an existing SubCO on that subcontract.
- Created SCOs will be linked to the PCO - When you create SCOs using this form, the created subcontract change orders will be linked to the PCO using the Related Items feature.
- The subcontracts do not have to be interfaced - You can create SCOs for subcontracts that are approved, or interfaced with the accounting modules using PM Interface.
Create SubCOs using PCO Detail Items
Follow the steps below to create SubCOs using PCO item detail.