Field Definitions: PM Update Projection Options Form
The following is a list of field descriptions for the PM Update Projections Options form.Many of the descriptions include links to other topics that provide additional information about or related to the topic.
Write Over Plugged Values
The Write Over Plugged Values radio options on the PM Update Projection Options form.
Never — Never write over existing plugged values.
Always — Always write over plugged values.
Only When Actual + Committed Costs Exceed Plugged Costs — Initialization will only write over plugged values when the actual plus remaining committed costs exceed the plugged costs.
Only When Actual + Committed Costs Exceed Plugged Costs, Keep as Plugged — Plugged values are only overwritten when the actual plus remaining committed costs exceed the plugged costs; however, values will remain flagged as ‘plugged’.This is the option used by most customers
Initialized Worksheet Detail Option
The Initialized Worksheet Detail Option drop-down on the PM Update Projection Options form.
None
Initialize Detail Projections with values
Initialize Detail Projections without values