Field Definitions: PM Daily Logs Form
The following is a list of field descriptions for the PM Daily Logs form. Many of the descriptions include links to other topics that provide additional information about or related to the topic.
Project
Log Date
Enter the date of this daily project log. The corresponding day of the week displays to the right.
Shortcuts
T or t |
Set the date to the current date. |
MMDD Four digit month and day |
Enter a four digit month and date (MMDD) and the system will automatically add the current year. |
+ |
The system will automatically set the date to tomorrow. |
+5 |
The system will automatically set the date to 5 days in the future. You can actually enter any value after the +, for example you can enter +7 to set the date to next week. |
- |
The system will automatically set the date to the previous day. |
The system will automatically set the date to 5 days in the past. Just like with +, you can enter any value after the -, for example you can enter -7 to set the date to the previous week. |
Daily Log
This field represents a specific log entry on the date entered in the Log Date field. For example, if this is the first entry of the day, enter a 1.
The value in this field can be up to five characters long and between -32,767 and 32,767.
Create a new daily log
The daily log number must be unique for each log date because it represents a specific entry on a specific log date.
There are a few ways to create a new daily log using this field:
Click the New Record icon (
) and select a date in the Log Date field. The system will populate the Daily Log field with the next available number. TAB through the field to create a new daily log.
Enter a '+' in this field and then press TAB to exit the field. The system will automatically create a new daily log and assign it the next available number.
Enter a daily log number that doesn't already exist and then press TAB to exit the field. The system will automatically create a new daily log. You can also press F4 to see a list of daily log numbers that have already been created.
Select an existing daily log
Enter an existing daily log number or press F4 to select one from a list.
Description
Document Type
Use this field to categorize the daily log that you are creating. Press F4to select a document type from a list.
Document types are created and maintained using the PM Document Types form. Click here for more information on document types.
Required when using 'Send with Transmittal'
If you select
, a document type must be selected in this field.Click here for an overview of the Create & Send feature.
Weather
Wind
Temperature: High
Temperature: Low
Include In Document
For each option listed, check the box to include the corresponding information on the PM Daily Project Log report.
Employees |
Conversations |
Crews |
Deliveries |
Subcontractors |
Accidents |
Equipment |
Visitors |
Activity |
|
Leave the box unchecked for information you want excluded from the Daily Project Log report.
Employees: Sequence
Employees: Employee
Specify the employee (from PM Firm Contacts or PR Employees) to which this daily log entry applies. Press F4 for a list of firm contacts or PR employees. You can also enter the first few characters of the sort name and the system will locate and display the first closest match.
You can only enter an employee (from PR Employees) if in PM Company Parameters you have checked the PR in Use box and assigned a PR company.
If you specify an employee that does not exist as an ‘our firm’ contact, that employee will be automatically added to PM Firm Contacts, with the Exclude from Lookups flag checked, once you save the record. (Note: The Exclude from Lookups flag is ignored when using the F4 lookup from this field; all ‘our firm’ contacts will display when using the ‘Firm Contacts’ lookup option, regardless of how you set the Exclude from Lookups flag. However, all other Firm Contact lookups in PM will exclude contacts with this flag checked.)
Employees: Start Time
Employees: End Time
Specify the time at which this employee stopped working for the day on this project, in 24-hour (for example, 17:00 for 5:00 p.m.). Typically, the end time comes after the start time; however, in cases where the end time falls on the next day, it will come before the start time. In this case, the system gives you a warning that the end time comes before the start time; however, the entry will be saved. When you print the PM Daily Project Log report, the times will accurately show the a.m./p.m. designation.
Employees: Phase
Employees: Worked
Employees: Location
Employees: Remarks
Use this field to enter any remarks or notes about this employee. For additional space in which to write more detailed notes, double-click on this field. The Grid Notes window will display, allowing you virtually unlimited space for your notes and information. There is however, a maximum allowance of 8k.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Crews: Sequence
Crews: Crew
Crews: Start Time
Crews: End Time
Specify the time at which this crew stopped working for the day on this project. Enter in 24-hour format (for example, 17:00 for 5:00 p.m.).
Typically, the end time comes after the start time; however, in cases where the end time falls on the next day, it will come before the start time. In this case, the system gives you a warning that the end time comes before the start time; however, the entry will be saved. When you print the PM Daily Project Log report, the times will accurately show the a.m./p.m. designation.
Crews: Supervisor
Crews: Foremen
Crews: Journeymen
Crews: Apprentices
Crews: Location
Crews: Remarks
Use this field to enter any remarks or notes about this crew. For additional space in which to write more detailed notes, double-click on this field. The Grid Notes window will display, allowing you virtually unlimited space for your notes and information. There is however, a maximum allowance of 8k.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Subcontractors: Sequence
Subcontractors: Firm
Enter the subcontractor or press F4 to select it from a list.
The sort name can be used instead of the firm number when selecting firms in PM module forms. Generally the sort name is the first several letters of the firm name. For example when creating a subcontract in the PM Subcontracts form for 'Bryan Electrical', you can enter the sort name 'bryan' in the Vendorfield instead of the firm number '10042'. The sort name of a firm is set up using the Sort Name field on the PM Firms form.
Subcontractors: Start Time
Subcontractors: End Time
Specify the time at which this subcontractor stopped working for the day on this project, in 24-hour format.
Typically, the end time comes after the start time; however, in cases where the end time falls on the next day, it will come before the start time. In this case, the system gives you a warning that the end time comes before the start time; however, the entry will be saved. When you print the PM Daily Project Log report, the times will accurately show the a.m./p.m. designation.
Subcontractors: Supervisor
Subcontractors: Foremen
Subcontractors: Journeymen
Subcontractors: Apprentices
Subcontractors: Location
Subcontractors: Remarks
Use this field to enter any remarks or notes about this subcontractor. For additional space in which to write more detailed notes, double-click on this field. The Grid Notes window will display, allowing you virtually unlimited space for your notes and information. There is however, a maximum allowance of 8k.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Equipment: Sequence
Equipment: EMCo
Equipment: Equipment
Equipment: Description
Equipment: Firm
Equipment: Quantity
Equipment: UM
Equipment: Location
Activity: Sequence
Activity: Description
Enter a description of the activity that occurred. For additional space in which to write more detailed notes, double-click on this field. The Grid Notes window will display, allowing you virtually unlimited space for your notes and information. There is however, a maximum allowance of 8k.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Activity: Location
Conversations: Sequence
Conversations: Firm
Conversations: Contact
Conversations: Description
Enter a description of the conversation. For additional space in which to write more detailed notes, double-click on this field. The Grid Notes window will display, allowing you virtually unlimited space for your notes and information. There is however, a maximum allowance of 8k.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Deliveries: Sequence
Deliveries: Firm
Deliveries: PO #
Enter the purchase order number that applies to the delivery or press F4 to select a PO from a list.
If you select a PO that has not yet been set up in PO Purchase Order Entry , you will need to create it now - the system does not automatically create a PO when you enter a new PO number. Press F5 while in this field to open PO Purchase Order Entry and create a new PO.
Deliveries: Material
Deliveries: Time
Deliveries: Location
Deliveries: Delivery Ticket
Accidents: Sequence
Accidents: Firm
Accidents: Employee
Accidents: Description
Use this tab to enter any notes about this item. The space allowance is virtually unlimited.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Accidents: Time
Accidents: Location
Visitors: Visitor
Visitors: Activity
Use this tab to enter any miscellaneous notes about this item. The space allowance is virtually unlimited.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Visitors: Arrived
Visitors: Departed
Visitors: Location
Sent To Firm
Enter the firm that should receive the document(s) generated using the Create and Send feature or press F4 to select a firm from a list.
Click here for an overview of the Create and Send feature.
Drag and Drop
To drag and drop firms/contacts to the distribution grid, double-click the Distribution tab (label) or select
. This displays the Project Firm Contacts list. You can then select a firm/contact and drag it to the grid.If you manually add a firm/contact to the grid that is not set up for the project, upon saving the record, the system displays a message indicating the firm/contact does not exist in PM Firms and gives you the option to add the firm/contact. Select Yes to add the firm/contact to the distribution list and to PM Firms. Select No to add the firm/contact to the distribution grid only.
Distribution defaults
When creating a new record, the Distribution tab will automatically populate with any PM firm contact set up as a distribution default.
For example, if a contact at an architecture firm should receive a copy of all drawing logs of document type 'ARCH', you can use the distribution default feature to set up that contact as a default for 'ARCH' documents. When drawing logs of that type are created, that contact will automatically populate on the Distribution tab.
Click here for more information on distribution defaults.
Using the sort name
The sort name can be used instead of the firm number when selecting firms in PM module forms. Generally the sort name is the first several letters of the firm name. For example when creating a subcontract in the PM Subcontracts form for 'Bryan Electrical', you can enter the sort name 'bryan' in the Vendorfield instead of the firm number '10042'. The sort name of a firm is set up using the Sort Name field on the PM Firms form.
Sent To Contact
Enter the contact that should receive the document(s) generated using the Create and Send feature, or press F4to select one from a list. Only contacts associated with the firm selected in the Sent To Firm field can be selected.
Contacts are associated with firms using PM Firm Contacts .
Distribution defaults
When creating a new record, the Distribution tab will automatically populate with any PM firm contact set up as a distribution default.
For example, if a contact at an architecture firm should receive a copy of all drawing logs of document type 'ARCH', you can use the distribution default feature to set up that contact as a default for 'ARCH' documents. When drawing logs of that type are created, that contact will automatically populate on the Distribution tab.
Click here for more information on distribution defaults.
Send
Check this box if the contact should receive communications generated using the Create and Send feature.
When this box is not checked, the contact can be manually added to a Create and Send email but they will not automatically populate in the To, Cc, or Bcc fields on the Message tab of the PM Send Documents form.
Click here for an overview of the Create and Send feature.
If a communication has already been sent
If this contact was added to an email generated using the Create and Send feature, this box will be checked.
Preferred Method
Use this field to select which type of communication should be sent to the contact when using the Create and Send feature. This field defaults based on the preferred method set up using PM Firm Contacts.
M -Print — Print a hard copy of the generated PDF document(s). When this option is selected, the contact will not receive a copy of the email body text.
E -Email — Send the generated PDF document(s) using email. The email address of the contact is pulled from the Email field on the Info tab of the PM Firm Contacts form. F -Fax — Send the generated PDF document(s) suing fax. The system will use the fax number set up on the PM Firm Contacts form.
Note:This option requires that you have a fax server set up in the PM Company Parameters .
field on the Info tab of
Send Type
Select how the contact should be added to the communication generated from the Create and Send feature: To, Cc, Bcc.
When a communication is created using the Create and Send feature (), the contact will automatically be added using the selection in this field.
Click here for an overview of the Create and Send feature.
If a communication has already been sent
If an email generated using the Create and Send feature has already been sent to the contact, this field will display how the contact was included on the last communication.
For example if the contact was added to an email in the Tofield on the PM Send Documents form, To will display in this field. When a new email is created using the Create and Send form, the contact will automatically populate in the Tofield.
Date Sent
This field displays the date a communication was sent to the contact using the Create and Send feature.
If several communications have been sent, the most recent date will display.
Notes
Enter any notes that relate to this contact. You can double click in the field if you need more space to enter information.
Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.
Spelling Check
Click the Spelling icon on the toolbar or select
to spell check the text in this field.