Company Add-Ons: Add-on Basis

Use the Add-On Basis section in PM Company Add-Ons to specify the add-on basis; that is, the amount on which to base the add-on cost.

You can specify to use a flat amount or have the calculation based on a percentage of the overall change order or the total costs for a specific cost type.

If the add-on is for additional costs (e.g. bonds), you can redirect the costs to a specific phase/cost type and/or contract item. If you wish to distribute the add-on amount to all phases on the change order with a specific cost type, leave the phase blank and enter only the desired cost type. The system will distribute the add-on amount proportionally to all phases on the change order with that cost type, adjusting the last phase/cost type for rounding (if necessary).

Example:

Add-on:

100

Basis:

Cost Type

Basis CT:

1 (Labor)

Percent:

10.00

Redirect CT:

7 (Burden)

Redirect Phase:

(blank)

Pending CO:

Phase

CT

Amount

Add-on Amt

02210-  -

1

300.00

30.00

03310-  -

1

300.00

30.00

04410-  -

1

  400.00

40.00

Total:

$1000.00

$100.00

Approved CO:

Phase

CT

Amount

02210-  -

1

300.00

7

30.00

03310-  -

1

300.00

7

30.00

04410-  -

1

400.00

7

40.00

Total:

$1100.00