JC Progress Units

You can use the JC Progress Units report for a list of JC Contract Items and their Cost Type, Unit of Measure, Estimated Units by selecting Job Cost > Reports > JC Progress Units.

The JC Progress Units lists JC Contract Items and their Cost Type, Unit of Measure, Estimated Units. In addition Units To This Period and To Date are given depending on the entered data parameters.

Report Parameters

Description

Company

Accept the default, or press F4 to select a company.

Beginning Contract

Select the Field Lookup button or press F4 to select the beginning contract.

Ending Contract

Select the Field Lookup button or press F4 to select the ending contract.

Beginning Date

Enter beginning date (MM/DD/YY)

Ending Date

Enter ending date (MM/DD/YY)

Include Phases/CT’s with Bill Flag?

checkbox to include phases and cost types with bill flag.