PM Pending Purchase Orders

You can use the PM Pending Purchase Orders report by selecting Project Management > Reports > PM Pending Purchase Orders.

The PM Pending Purchase Orders report, sorted by Project and Purchase Order (PO), prints material detail not yet interfaced to Job Cost. Unassigned detail entries (no PO #) will sort before assigned PO's. Unassigned PO's will sort by change order type (approved/pending), change order number, then by item. The original unassigned PO's will print last. The report shows the material number, change order number (if applicable), change order item, phase, cost type, units, UM, unit cost, and amount.

Report Parameters

Description

Company

Accept the default, or press F4 to select a company.

Beginning Project

Select the Field Lookup button or press F4 to select the beginning project.

Ending Project

Select the Field Lookup button or press F4 to select the ending project.

Beginning Purchase Order

Click the Field Lookup button or press F4 to select the beginning purchase order.

Ending Purchase Order

Click the Field Lookup button or press F4 to select the ending purchase order.