Apply Swell/Yield Factors
-
Open a job in the Manage Earthwork Estimates
screen.
Note: To open a job in the Manage Earthwork Estimates screen, click Estimating > Earthwork > Manage Earthwork Estimates in the All Tasks pane. Click Open Existing Job. Then select the job you want to open, and click OK.
- Select the Summary tab, if it is not already active.
-
Click Detail
on the speedbar.
- Select the factor you want to change in the Swell/Yield columns. You can change both the swell and yield for the selected material.
-
In the Swell field, click
to increase or decrease the swell factor for the material.
-
In the Yield field, click
to increase or decrease the yield factor for the material. If needed, you can calculate the yield based on the swell, by doing the following:
- Click Calc.
-
In the Swell Factor field, click
to increase or decrease the swell factor for the material.
-
In the Original Density field, click
to increase or decrease the density percentage for the original material.
-
In the Design Density field, click
to increase or decrease the density percentage for the final material.
- Click OK.
- Click OK.
- The quantities are recalculated based on the new swell/yield factor and appear in the Adjusted Quantity column.