Change the Elevation of an Existing Spot
-
Open a job in the Manage Earthwork Estimates
screen.
Note: To open a job in the Manage Earthwork Estimates screen, click Estimating > Earthwork > Manage Earthwork Estimates in the All Tasks pane. Click Open Existing Job. Then select the job you want to open, and click OK.
- Select the Takeoff tab, if it is not already active.
-
In the Active Layer field on the toolbar, click
to select the layer for which you want to change the spot elevations.
-
Click Select
on the speedbar.
- Select the spot elevation you want to change.
-
Click Prop
on the speedbar.
- In the Elevation field, enter the new spot elevation.
- Click OK.