Field Definitions: PM CO Items Initialize Form
The following is a list of field descriptions for the PM CO Items Initialize form. Many of the descriptions include links to other topics that provide additional information about or related to the topic.
Beginning/Ending Contract Item
Contract Item Start Month
Enter the contract item 'Start Month' by which to restrict initialization. Only contract items with this start month (in JC Contract Items) that meet all other restriction criteria will be initialized as change order items.
Leave blank to include all contract items within the specified range, regardless of start month.
Contract Item Bill Group
Enter the contract item 'Bill Group' to restrict by. Only contract items assigned this bill group (in JC Contract Items) that meet all other restriction criteria will be initialized as change order items.
Leave blank to include all contract items within the specified range, regardless of bill group.
Include Lump-Sum (LS) Contract Items
Use Contract Item Descriptions
Check this box to use the contract item's description as the change order item's description.
Leave this box unchecked if you do not want to use contract item descriptions as change order item descriptions. Change order item descriptions will default from the PCO or ACO description.
Set Fixed Price Flag as checked
Enabled only if initializing items for PCO’s where the Int/Ext flag is set to ‘E-External’.
Check this box to set the 'Fixed Amount' flag to Y (checked) for all change order items initialized to the grid.
Leave this box unchecked to set the ‘Fixed Amount’ flag to N (unchecked) for all change order items initialized to the grid.
If you elect to 'include LS contract items' for initialization, the 'Fixed Amount’ flag will be checked for all items, regardless of how you set this flag.
Set Generate Detail Flag as checked
Calculate Add'l Units/Amount to Equal Billing
Check this box to initialize additional units or amounts for each contract item based on billing values. Additional units and amounts will be calculated based on BilledUnits or Billed Amounts in JCCI (Contract Items), plus UnitsBilled or AmtBilled for non-interfaced billings from JBIT (Bill Items), less ContractUnits or ContractAmt from JCCI.
Leave this box unchecked if you do not want additional units or amounts calculated based on billing values. Additional Units and Amount columns will be set to 0.00.
The Thru Month specified below determines the month through which billings are pulled for calculating additional units/amounts. Calculations will include values posted in months equal to or less than the Thru Month.
Positive Additional Units/Amount only
Enabled only if the Calculate Add’l Units/Amount to Equal Billing option is checked above.
Check this box to show only calculations resulting in positive units or amounts in the grid. Calculations resulting in negative units/amounts will be set to 0.00 for the contract item.
Leave this box unchecked to show all calculations in the grid, regardless of whether they are positive or negative values.
Thru Month
Contract Item
CO Item
Enter a number for this change order item, up to 10 characters, or enter ‘+’ to assign the next sequential number available for the change order. You can also leave this field blank and use the ‘Create CO Items’ feature to auto-generate numbers for all items on the change order.
Description
Enter a description of this change order item, up to 60 characters. Initially defaults either the contract item's description (if 'Use Contract Item Description' flag is checked) or the description defined for the pending/approved change order (if 'Use Contract Item Description' flag is unchecked).
Additional Units
For unit-based items only, specify the additional units for this change order item. This is the number of units by which this item changes the contract item's units. Initially defaults a value based on the following:
If you checked the Calculate Add'l Units/Amount to equal billing box (above), default will be based on this contract item's BilledUnits in JCCI (Contract Items), plus UnitsBilled for non-interfaced billings from JBIT (Bill Items), less ContractUnits from JCCI. If the calculation produced negative units and you checked the Positive Additional Units/Amount Only option, default will be 0.00.
If you did not check the Calculate Add'l Units/Amount to equal billing box, or the item is LS, default will be 0.00. (If LS, field is display only and default cannot be overridden.)
Amount
Specify the additional amount for this change order item. This is the amount by which this item changes the contract item's units. Initially defaults a value based on the following:
LS Items
If using the ‘Calculate Additional Units/Amount to Equal Billing’ option (above), default will be based on this contract item's BilledAmt in JCCI (Contract Items), plus AmtBilled for non-interfaced billings from JBIT (Bill Items), less ContractAmt from JCCI. If the calculation produced a negative amount and you checked the ‘Positive Additional Units/Amount Only’ option, default will be 0.00.
If not using the ‘Calculate Additional Units/Amount to Equal Billing’ option, default will be 0.00.
Unit-based Items
Defaults an amount based on the units x the unit price. Changes to this amount will cause the unit price to be recalculated.
Fixed Amount
Enabled only for PCOs with the ‘I/E’ flag set to E (External).
Check this box to set this item's amount as 'fixed'. The Amount initialized for this change order item will exclude any markup and/or add-on amounts. (Note: This option is automatically checked for all LS items, regardless of how the 'Set Fixed Price…' flag is set in the filter criteria. It is also automatically checked for all items on an 'internal' pending change order.)
Leave this box unchecked if this item's amount is not 'fixed'. The Amount initialized for this change order item will include markup and/or add-on amounts.
This flag defaults as unchecked for all ACO items and is disabled.
Generate Detail
Check this box to automatically generate phase detail for this change order item. Phase detail will be generated using the same process used when generating phase detail in PM Pending Change Orders and PM Approved Change Orders .
Leave this box unchecked if you want to manually enter or generate phase detail for this change order item.
Clear Items/Refresh Items/Create CO Items/Process CO Items
Click the Clear button to clear the grid and start over.
Click the Refresh button to populate the grid once you have entered filter criteria and set default options. Only contract items meeting the criteria will be added to the grid. You can then enter the appropriate values and edit the flag settings as necessary. You can also delete unwanted items from the grid by highlighting the item, then clicking the Delete button in the toolbar. To clear the grid and start over, click the Clear button.
Click the Create CO Items button to auto-generate change order items based on the next sequential number available for the change order. When clicked, contract items not already assigned a CO Item and having additional units or amounts (LS) not equal to 0.00, will be assigned the next sequential CO Item.
Once you are satisfied with the entries in the grid, click the Process CO Items button. This will initialize the change order items and add them to the appropriate change order items grid (i.e. PCO Items or ACO Items).