Field Definitions: PM Projection Codes Form

The following is a list of field descriptions for the PM Projection Codes form. Many of the descriptions include links to other topics that provide additional information about or related to the topic.

Units

The Unit of Measure field on the Info tab allows you to specify the units you want to accumulate for this projection code. When entering projections using the PM Cost Projections form, you can plug units and have the adjustements spread to associated phase/cost types.

For information about the spread option, see About Using the Spread Option for Cost Projections.

This will be the final units on the projection code

When creating a projections using the PM Cost Projections form, the value entered in this field will populate in the Final Units field on the projection code (PM Cost Projections> Grid tab> Final Units).

Proj Code Units

The Proj Code Units checkbox on the PM Projection Codes form, Phase/Cost Types tab.

Select this checkbox to include this cost type when projecting units.

The Unit of Measure field on the Info tab allows you to specify the units you want to accumulate for this projection code. When entering projections using the PM Cost Projections form, you can plug units and have the adjustments spread to associated phase/cost types.

If you created project codes using the Create Project Codes from Phase option (Task menu), this checkbox defaults as selected for any cost type on the phase where the UM matches the UM of the cost type with the PhaseUnitFlag​ checkbox selected. You may override as needed.

Note: If this is a linked cost type and you want its units updated automatically when posting units to the primary cost type, you must select this checkbox. If it is not selected, changes to the primary cost type will not update this cost type.

For information about common UMs, see About Setting Common UMs for Projection Codes.

Spread %

Use this field to select how the plugged values entered on a projection code will be distributed to the associated phases/cost types.

For more information about the spread option, see About Using the Spread Option for Cost Projections.

Make sure you distribute 100%!

The spread percentage on all of the phases/cost types should total 100%.

The current total displays at the top of the form next to the Projection Code field.

Note: This field is only enabled when Defined at Projection Code is selected in the Spread Option field on the PM Company Parameters form (Projections tab).

Notes

Enter any notes that apply to the projection code.

Spelling Check

Click the Spelling icon on the toolbar or select Tools > Spelling to spell check the text in this field.

Add a Standard Note

Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.

To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.