JC Cost Report With ACO

You can use the JC Cost Report With ACO report for JC Costs with Approved Change Order Detail by selecting Job Cost > Reports > JC Cost Report With ACO.

Report Parameters

Description

Company

Accept the default, or press F4 to select a company.

Through Month

Enter through month (MM/YY).

Beginning Job

Select the Field Lookup button or press F4 to select the beginning job.

Ending Job

Select the Field Lookup button or press F4 to select the ending job.

Beginning Phase

Select the Field Lookup button or press F4 to select the beginning phase.

Ending Phase

Select the Field Lookup button or press F4 to select the ending phase.

Beginning Project Manager

Select the Field Lookup button or press F4 to select the beginning project manager.

Ending Project Manager

Select the Field Lookup button or press F4 to select the ending project manager.

Page by Job?

checkbox to have page break per job.