Enter Contract Invoice Screen Field Reference
The Enter Contract Invoice screen contains the following tabs:
General tab
Field |
Description |
---|---|
Invoice Date |
Enter the transaction date of the contract invoice or click |
Posting Date |
Enter the posting date for the contract invoice or click |
Posting Group |
Enter the code of the Contract Invoice Posting Group screen for the contract invoice or click |
Payment Terms |
Initially displays the default Payment Terms screen for the customer. If you want to modify the payment terms or if the customer is a new customer, enter the payment terms for the contract invoice or click |
Invoice Through Date |
Initially displays the date based on the current month, the default invoice through day entered in Project Billing, and the current year. If you want to override this date, enter the new date or click |
Invoice Format |
Initially displays the default invoice form for the project billing format. To change the invoice form, enter the name of the invoice form you want to use for the contract invoice or click |
Continuation Format |
If the project billing format is AIA, initially displays the default continuation form for the billing format. To change the continuation form, enter the name of the form you want to use for continuation reports or click |
Pending COR Format |
Initially displays the default pending COR form for the project billing format. To change the form, enter the name of the form you want to use for pending change order requests or click |
Invoice Due Date |
Initially displays the date on which payment for the contract invoice is due based on the invoice date and the payment terms. If you want to override this date, enter the new date or click |
Discount Due Date |
Initially displays the date on which the discounted payment is due based on the invoice date and the payment terms. If you want to override this date, enter the new date or click |
Owner |
Enter the Users screen for the contract invoice owner or click |
Assigned To |
Initially displays the ID for the contract invoice owner. Once the Contacts/Routing tab is completed, displays one of the following:
|
Priority |
Click
|
Memo |
Enter any comments or notes about the contract invoice. |
Invoice Description |
Enter a description for the contract invoice that can be printed on the invoice form. You can enter formatted text in this field. Click |
AIA Invoice Detail tab
Use the AIA Invoice Detail tab to manage the line item details for the invoice. This tab is only visible if the billing format is AIA. The Billing Code grid is populated with all the detail-level billing codes defined in the Project screen for the project billing combination selected in the header. If you didn't select the Track Revenue by Project Cost Code checkbox on the Billing tab of the Project screen, enter the line item details in this grid. If you did select the checkbox, the fields in the Billing Code grid are display only; use the Project Cost Code grid to enter the line item details. Click Expand All in the quick link bar to display cost codes for each billing code.
Field |
Description |
---|---|
Billing Code |
Displays the billing code defined on the Project screen for the project billing format and customer combination. |
Owner CO |
Displays the owner change order if any, associated with the billing code line item. |
Name |
Displays the name of the billing code. |
Sort |
Displays the text used for the billing code in lookup lists. |
Sales Tax Authority |
Displays the name of the sales tax authority for the billing code line item. |
Taxable |
Displays whether the billing code line item is taxable. If this checkbox is not selected, the taxable amount and the tax amount are set to zero. If needed, click |
Scheduled Value |
Displays the current scheduled amount for the billing code line item. |
Previous Work Complete |
Displays the dollar amount of the previous work completed for the billing code line item. |
% Work Completed |
Displays the percentage of work completed for the billing code line item. If needed, enter a new value to update the work completed percentage for the billing code line item. The Current Work Completed field and Retainage to Date field are updated based on the value you enter in this field. |
Current Work Completed |
Displays the dollar amount of current work completed for the billing code line item based on the percentage work completed. If needed, enter a new value to update the work completed dollar amount for the billing code line item. The % Work Completed field and Retainage to Date field are updated based on the value you enter in this field. |
Stored Material |
Displays the value of the stored materials for the billing code line item. If needed, enter a new value to update the stored materials used for the billing code line item. The % Work Completed field and Retainage to Date field are updated based on the value you enter in this field. |
Retainage to Date |
Displays the calculated amount of retainage to date for the billing code line item. If you want to override this amount, enter a new value to update the retainage to date for the billing code line item. Enter Note: Retainage billed on the invoice is not displayed on the screen, but it is printed on the default invoice form.
|
Project Cost Code grid - When you click | |
Project |
Displays the code for the project for the cost code line item. |
Division |
Displays the division associated with the cost code project. |
Cost Code |
Displays the cost code for the cost code line item. |
Owner CO |
Displays the code for the owner change order for the cost code line ite |
Sales Tax Authority |
Displays the sales tax authority for the cost code line item. |
Taxable |
Displays the taxable status for the cost code line item. If needed, you can change the taxable status for the cost code line item. If the line item is not taxable, the taxable amount in all lines of the associated Tax Detail grid will be zero. |
Scheduled Value |
Displays the current scheduled amount from the cost code line item. |
Previous Work Complete |
Displays the dollar amount of the previous work completed for the cost code line item. |
% Work Completed |
Enter the current percent of work completed for the cost code line item. The Current Work Completed field and Retainage to Date field are updated based on the value you enter in this field. If you selected the Generate Billing Amount from WIP Entries checkbox on the Project screen, ProContractor calculates the percentage of work completed based on the work in progress (WIP) entries made through Invoice Through Date and then updates the current work completed, stored material, and retainage to date. |
Current Work Completed |
Displays the calculated dollar amount of current work completed for the cost code line item based on the percent work completed and the stored material. If you want to override this amount, enter the amount of work completed. The % Work Completed field and Retainage to Date field are updated based on the value you enter in this field. |
Stored Material |
Displays the calculated value of the stored materials used for the cost code line item. If you want to override this value, enter the value of the stored materials for the cost code line item. The % Work Completed field and Retainage to Date field are updated based on the value you enter in this field. |
Retainage to Date |
Displays the calculated amount of retainage to date for the cost code line item based on the percent work completed. If you want to override this amount, enter the retainage to date. Enter |
Tax Detail grid - When you click | |
Tax Authority |
Displays the codes of the tax authorities for the line item. You cannot modify or delete the primary tax authority from the Tax Detail grid. |
Name |
Displays the names of the tax authorities for the line item. |
Taxable Amount |
Displays the taxable amount of the line item for the tax authority, which is calculated based on the current amount. If you want to modify the taxable amount, enter the taxable amount. |
Tax Amount |
Displays the tax amount of the line item for the tax authority, which is calculated based on the current amount. If you want to modify the tax amount, enter the tax amount. |
Non-Taxable Amount |
Displays the non-taxable amount (current amount - taxable amount) of the line item for the tax authority. |
Retainage Taxable Amount |
Displays the retainage taxable amount of the line item for the tax authority, which is calculated based on the current retainage to date. If tax isn't being charged on unreleased retainage, you can modify the retainage taxable amount. |
Retainage Tax Amount |
Displays the retainage tax amount of the line item for the tax authority, which is calculated based on the retainage taxable amount. If tax isn't being charged on unreleased retainage, you can modify the retainage tax amount. |
Retainage Non-Taxable Amount |
Displays the retainage non-taxable amount (retainage taxable amount - retainage taxable amount) of the line item for the tax authority. If tax isn't being charged on unreleased retainage, you can modify the retainage non-taxable amount. |
Footer | |
Total Scheduled Value |
Displays the total scheduled value for the line items. |
Total Current Work Complete |
Displays the total current work complete for the line items. |
Total Stored Material |
Displays the total stored materials for the line items. |
Total Retainage to Date |
Displays the total retainage to date for the line items. |
Total Invoice Amount |
Displays the total invoice amount for the line items. |
Percentage Complete Invoice Detail tab
Use the Percentage Complete Invoice Detail tab to manage the line item details for the invoice. This tab is only visible if the billing format is Progress Billing. The Billing Code grid is populated with all the detail-level billing codes defined in the Project screen for the project billing combination selected in the header. If you didn't select the Track Revenue by Project Cost Code checkbox on the Billing tab in the Project screen, enter the line item details in this grid. If you did select the checkbox, the fields in the Billing Code grid are display only; use the Project Cost Code grid to enter the line item details. Click Expand All in the quick link bar to display cost codes for each billing code.
Field |
Description |
---|---|
Billing Code |
Displays the billing code defined on the Project screen for the project billing format and customer combination. |
Owner CO |
Displays the owner change order if any, associated with the billing code line item. |
Name |
Displays the name of the billing code. |
Sort |
Displays the text used for the billing code in lookup lists. |
Sales Tax Authority |
Displays the name of the sales tax authority for the billing code line item. |
Taxable |
Displays whether the billing code line item is taxable. If this checkbox is not selected, the taxable amount and the tax amount are set to zero. If needed, click |
Contract Amount |
Displays the contract amount for the billing code line item. |
Previous Amount |
Displays the previous amount for the billing code line item. |
Percentage Completed |
Displays the percent of work completed for the billing code line item If needed, enter the percent of work completed for the billing code line item. The current amount and retainage to date update based on the percent entered. |
Current Billing Amount |
Displays the calculated current amount of work completed for the billing code line item. If needed, enter the current dollar amount of the work completed for the billing code line item. The percentage completed and retainage to date update based on the amount entered. |
Retainage to Date |
Displays the calculated retainage to date for the billing code line ite If needed, enter the retainage to date for the billing code line item. Enter |
Project Cost Code grid - When you click | |
Project |
Displays the code for the project for the project cost code. |
Division |
Displays the division associated with the project. |
Cost Code |
Displays the cost code for the cost code line item. |
Owner CO |
Displays the code for the owner change order for the cost code line ite |
Sales Tax Authority |
Displays the sales tax authority for the cost code line item. |
Taxable |
Displays the taxable status for the cost code line item. If needed, you can change the taxable status for the cost code line item. If the line item is not taxable, the taxable amount in all lines of the associated Tax Detail grid will be zero. |
Contract Amount |
Displays the contract amount for the cost code line item. |
Previous Amount |
Displays the previous amount for the cost code line item. |
Percent Completed |
Displays the percent of work completed for the cost code line item. If you want to override this amount, enter the percent of work completed. The current amount and retainage to date update based on the percent entered. If you selected the Generate Billing Amount from WIP Entries checkbox on the Project screen, ProContractor calculates the percentage of work completed based on the work in progress (WIP) entries made through the Invoice Through Date and then updates the current amount and retainage to date. |
Current Billing Amount |
Displays the calculated current amount of work completed for the cost code line item. If you want to override this amount, enter the current amount of work completed. The percentage completed and retainage to date update based on the amount entered. |
Retainage to Date |
Displays the calculated retainage to date for the cost code line item. If you want to override this amount, enter the retainage to date. Enter |
Tax Detail grid - When you click | |
Tax Authority |
Displays the codes of the tax authorities for the line item. You cannot modify or delete the primary tax authority from the Tax Detail grid. |
Name |
Displays the names of the tax authorities for the line item. |
Taxable Amount |
Displays the taxable amount of the line item for the tax authority, which is calculated based on the current amount. If you want to modify the taxable amount, enter the taxable amount. |
Tax Amount |
Displays the tax amount of the line item for the tax authority, which is calculated based on the current amount. If you want to modify the tax amount, enter the tax amount. |
Non-Taxable Amount |
Displays the non-taxable amount (current amount - taxable amount) of the line item for the tax authority. |
Retainage Taxable Amount |
Displays the retainage taxable amount of the line item for the tax authority, which is calculated based on the current retainage to date. If tax isn't being charged on unreleased retainage, you can modify the retainage taxable amount. |
Retainage Tax Amount |
Displays the retainage tax amount of the line item for the tax authority, which is calculated based on the retainage taxable amount. If tax isn't being charged on unreleased retainage, you can modify the retainage tax amount. |
Retainage Non-Taxable Amount |
Displays the retainage non-taxable amount (retainage taxable amount - retainage taxable amount) of the line item for the tax authority. If tax isn't being charged on unreleased retainage, you can modify the retainage non-taxable amount. |
Footer | |
Total Contract Amount |
Displays the total contract amount for the line items. |
Total Current Amount |
Displays the total current amount for the line items. |
Total Retainage to Date |
Displays the total retainage to date amount for the line items. |
Total Invoice Amount |
Displays the total invoice amount for the line items. |
Units Complete Invoice Detail tab
Use the Units Complete Invoice Detail tab to manage the line item details for the invoice. This tab is only visible if the billing format is Unit Billing. The Billing Code grid is populated with all the detail-level billing codes defined in the Project screen for the project billing combination selected in the header. If you didn't select the Track Revenue by Project Cost Code checkbox on the Billing tab in the Project screen, enter the line item details in this grid. If you did select the checkbox, the fields in the Billing Code grid are display only; use the Project Cost Code grid to enter the line item details. Click Expand All in the quick link bar to display cost codes for each billing code.
Field |
Description |
---|---|
Billing Code |
Displays the billing code defined on the Project screen for the project billing format and customer combination. |
Owner CO |
Displays the owner change order if any, associated with the billing code line item. |
Name |
Displays the name of the billing code. |
Sort |
Displays the text used for the billing code in lookup lists. |
Sales Tax Authority |
Displays the name of the sales tax authority for the billing code line item. |
Taxable |
Displays whether the billing code line item is taxable. If this checkbox is not selected, the taxable amount and the tax amount are set to zero. If needed, click |
Contract Quantity |
Displays the contract quantity for the billing code line item. |
Unit of Measure |
Displays the unit of measure for the billing code line item. |
Unit Price |
Displays the price per unit for the billing code line item. |
Previous Quantity |
Displays the quantity completed in the previous period for the billing code line item. |
Current Period Quantity |
Displays the quantity for the current period for the billing code line item. If needed, enter the quantity for the current period for the billing code line item. The current period amount, project-to-date amount, and retainage to date update based on the quantity entered. |
Current Period Amount |
Displays the calculated amount for the current period for the billing code line item. If you want to override this amount, enter the current period amount. |
Amount Project To Date |
Displays the calculated project-to-date amount for the billing code line item. |
Quantity Completed To Date |
Displays the to-date quantity completed for the billing code line item. |
Retainage To Date |
Displays the calculated retainage to date amount for the billing code line item. If you want to override this amount, enter the retainage to date. Enter |
Project Cost Code grid - When you click | |
Project |
Displays the code for the project for the project cost code. |
Division |
Displays the division associated with the project. |
Cost Code |
Displays the cost code for the cost code line item. |
Owner CO |
Displays the code for the owner change order for the cost code line ite |
Sales Tax Authority |
Displays the sales tax authority for the cost code line item. |
Taxable |
Displays the taxable status for the cost code line item. If needed, you can change the taxable status for the cost code line item. If the line item is not taxable, the taxable amount in all lines of the associated Tax Detail grid will be zero. |
Contract Quantity |
Displays the contract quantity for the cost code line item. |
Unit of Measure |
Displays the unit of measure for the cost code line item. |
Unit Price |
Displays the price per unit for the cost code line item. |
Previous Quantity |
Displays the quantity completed in the previous period for the billing code line item. |
Current Period Quantity |
Enter the quantity for the current period for the cost code line item. The current period amount, project-to-date amount, and retainage to date update based on the quantity entered. |
Current Period Amount |
Displays the calculated amount for the current period for the cost code line item. If you want to override this amount, enter the current period amount. If you selected the Generate Billing Amount from WIP Entries checkbox on the Project screen, ProContractor calculates the current period amount based on the work in progress (WIP) entries made through the Invoice Through Date and then updates the current period quantity and the current period amount in the Units Complete grid. |
Quantity Completed To Date |
Displays the to-date quantity completed for the billing code line item. |
Amount Project to Date |
Displays the calculated project-to-date amount for the cost code line item. |
Retainage to Date |
Displays the calculated retainage to date amount for the cost code line item. If you want to override this amount, enter the retainage to date. Enter |
Tax Detail grid - When you click | |
Tax Authority |
Displays the codes of the tax authorities for the line item. You cannot modify or delete the primary tax authority from the Tax Detail grid. |
Name |
Displays the names of the tax authorities for the line item. |
Taxable Amount |
Displays the taxable amount of the line item for the tax authority, which is calculated based on the current amount. If you want to modify the taxable amount, enter the taxable amount. |
Tax Amount |
Displays the tax amount of the line item for the tax authority, which is calculated based on the current amount. If you want to modify the tax amount, enter the tax amount. |
Non-Taxable Amount |
Displays the non-taxable amount (current amount - taxable amount) of the line item for the tax authority. |
Retainage Taxable Amount |
Displays the retainage taxable amount of the line item for the tax authority, which is calculated based on the current retainage to date. If tax isn't being charged on unreleased retainage, you can modify the retainage taxable amount. |
Retainage Tax Amount |
Displays the retainage tax amount of the line item for the tax authority, which is calculated based on the retainage taxable amount. If tax isn't being charged on unreleased retainage, you can modify the retainage tax amount. |
Retainage Non-Taxable Amount |
Displays the retainage non-taxable amount (retainage taxable amount - retainage taxable amount) of the line item for the tax authority. If tax isn't being charged on unreleased retainage, you can modify the retainage non-taxable amount. |
Footer | |
Total Current Period Amount |
Displays the total amount for the current period for the line items. |
Total Project to Date |
Displays the total amount for the project to date for the line items. |
Total Retainage to Date |
Displays the total retainage to date amount for the line items. |
Total Invoice Amount |
Displays the total invoice amount for the billing line items. |
Lien Releases tab
Use the Lien Release tab to specify how ProContractor will create a lien release record when the invoice is posted. Each row in the grid is a lien notice associated with the project.
Field |
Description |
---|---|
Lien Notice Number |
Displays the lien notice number. |
Project |
Displays the project for the lien notice. |
Remaining Balance |
Displays the remaining balance for the lien notice. |
Action |
By default, displays the action selected on the Lien Management Settings screen. If needed, click
|
Release Sent Date |
Enter the date the lien release was sent or click |
Release Through Date |
Enter the date the lien was released through or click |
Release Amount |
By default, displays the amount of the invoice without tax. If needed, enter the amount of the lien being released. If the release amount is equal to the remaining balance, the action will default to a final release. |
Release Description |
By default, displays |
Create Lien Release Notice Form |
Select the checkbox to indicate that ProContractor will create the lien notice document when the invoice is posted based on the form selected on the Enter Customer Lien Notice & Release screen for the release type and attach it to the lien notice record. |
Lien Notice Description |
Displays the lien notice description. |
Contacts/Routing tab
Each row in the grid is a contact associated with the document. Click Add Document Routing Distribution Group to add users from one or more document routing distribution groups to the tab. The Document Routing Distribution Control checkbox on the Document Management Settings screen must be selected for the routing fields to be enabled. Click to add a row to the grid. Click
to delete the active row from the grid.See Grids for tips on using grids in ProContractor.
If you are reviewing the document, update the Status and Memo from User fields.
Field |
Description |
---|---|
One Time Contact |
Select the checkbox to indicate whether this contact is a one-time contact. |
Contact Type |
Enter the Contact Type screen for this contact or click |
Name |
Enter the name of an existing Contact screen or click Tip: You can add new contacts or modify existing contacts from the lookup window.
To add a contact, click New in the List of Contacts lookup window and complete the fields on the Contact screen popup window. When you are finished, click OK to save the contact. To modify a contact, in the List of Contacts lookup window, click on the contact you want to modify and click Open. Modify the fields on the Contact screen popup window as needed. When you are finished, click OK to save the contact. |
Role |
Click
|
E-mail As |
Click
|
Notes |
Enter any comments or notes about the routing. You can enter formatted text in this field. Click |
Routing Type |
Click
|
Routing Date |
Enter the routing date or click |
Routing Due Date |
Enter the date the contact's response is expected or click |
Routing Priority |
Click
|
Routing Status |
Enter the code for the Document Management Types screen for the routing distribution or click |
Closed Date |
Enter the date the routing distribution is closed or click |
Routing Memo To User |
Enter any comments or notes about the document to the user on this line. If you are the user on this line, other users can enter memos to you here. You can enter formatted text in this field. Click |
Routing Memo From User |
Enter any comments or notes about the document if you are the user on this line. This memo appears from you to all other users. You can enter formatted text in this field. Click |
Routing Created By |
Displays the user who added the contact to the document and the date and time the contact was added. |
Company |
Displays the company for the contact. |
E-mail Address |
Display the e-mail address for the contact. |
Work Phone |
Displays the work phone number for the contact. |
Extension |
Displays the work phone extension for the contact. |
Cell Phone |
Displays the cell phone number for the contact. |
Main Address Street 1 |
Displays the first line of the contact's main address. |
Main Address Street 2 |
Displays the second line of the contact's main address. |
Main Address City |
Displays the city of the contact's main address. |
Main Address State |
Displays the state of the contact's main address. |
Main Address Zip |
Displays the zip code of the contact's main address. |
Main Address Country |
Displays the country of the contact's main address. |
Activity/History tab
Use this tab to record actions taken on the document and view the history of the document.
Field |
Description |
---|---|
Document Activity sub-tab - Use this sub-tab to record actions taken on the document. ProContractor automatically enters activities for printing the PDF file using the On Save of Document options, sending an e-mail with the PDF file attached, and importing daily field report information into ProContractor. In addition, you can enter other activities manually based on the activity types you defined on the Document Management Types screen. Click | |
System Generated |
Indicates whether ProContractor automatically created the row. If the checkbox is selected, the row cannot be modified or deleted. This field is display only. |
Date |
Enter the date the activity occurred or click |
Time |
Enter the time the activity occurred. |
Type |
Enter the code for the Document Management Types screen or click |
Description |
Enter a description of the activity. |
Memo |
Enter any comments or notes about the activity. You can enter formatted text in this field. Click |
Document History sub-tab - This sub-tab records details every time the document is saved, including when it was saved, who saved it, and the owner. If a PDF file was created when the document was saved, you can view the document. | |
Change Comment |
If you are modifying the document, enter the reason for the changes. You can enter formatted text in this field. Click |
Revision History grid - Each row in the grid is a revision of the document. The fields are display only. | |
Revision Number |
Displays the number for the document revision. |
Modified Date |
Displays the date the revision was saved. |
Modified By |
Displays the user who saved the revision. |
Owner |
Displays the document owner at the time the revision was saved. |
Change Comment |
Displays the change comment saved with the revision. |
Document File |
Click View to view the PDF file created when the document was saved. If the PDF file was not created the button is disabled. |
Referenced Documents tab
Use this tab to manage documents that are related to the document. The sub-tabs show documents which are referenced by the current document and documents that reference the current document.
Field |
Description |
---|---|
Documents This Document References sub-tab - Use this sub-tab to attach related documents to this document. Most of the fields are display only. The only enterable fields are Type, Document, and Attach when E-mailing Doc. Click | |
Type |
Click |
Document |
Enter the code for the document to attach or click |
Attach when Emailing Doc |
Select the checkbox to have ProContractor include the document as an attachment when sending an e-mail using the On Save of Document E-mail checkbox. |
Description |
Displays the description of the document. |
Date |
Displays the date of the document. |
Due Date |
Displays the due date for the document. |
Owner |
Displays the owner of the document. |
Priority |
Displays the priority of the document. |
Status |
Displays the status of the document. |
Documents That Reference This Document sub-tab - Use this sub-tab to view documents that reference this document. | |
This document appears as an Item on the following Transmittals and Issues grid - Use this grid to attach transmittals and issues for the same project to the document. Most of the fields are display only. The only enterable fields are the Type and Document fields. When you add a transmittal or issue on this tab, the document is added to the Referenced Documents tab on the corresponding transmittal or issue. If you delete the transmittal or issue document from this tab, the document is deleted from the Referenced Documents tab on the corresponding transmittal or issue. Click | |
Type |
Click |
Document |
Enter the code for the document to attach to the transmittal or click |
Description |
Displays the description of the document. |
Date |
Displays the date of the document. |
Due Date |
Displays the due date for the document. |
Owner |
Displays the owner of the document. |
Priority |
Displays the priority of the document. |
Status |
Displays the status of the document. |
This document is also referenced by the following documents grid - Use this grid to attach documents for the same project to the document. Most of the fields are display only. The only enterable fields are Type and Document. When you add a document on this tab, the document is added to the Referenced Documents tab on the corresponding document. If you delete the document from this tab, the document is deleted from the Referenced Documents tab on the corresponding document. Click | |
Type |
Click |
Document |
Enter the code for the document to attach to the transmittal or click |
Description |
Displays the description of the document. |
Date |
Displays the date of the document. |
Due Date |
Displays the due date for the document. |
Owner |
Displays the owner of the document. |
Priority |
Displays the priority of the document. |
Status |
Displays the status of the document. |
Binder tab
This tab contains the following sub-tabs:
Field |
Description |
---|---|
Binder sub-tab - If user-defined fields exist for this function, the Binder sub-tab appears. Otherwise, the information appears on the Binder tab with no sub-tabs. Each row in the grid is a binder item. A binder item is an item associated with the record. You can attach a file to a binder item and set reminders for binder items. It can be useful to create binder items for contracts, legal documents, and photos. Use the Binder Item Types screen to create and manage categories for binder items. A paper clip Click When you create the pdf document for a contract invoice, multiple binder items are automatically created —one for each individual format that is valid for the invoice (based on its billing format) and one that includes all formats. The binder item for the Pending COR format is created only if there are pending change order requests for the project. Binder items for a contract invoice can also be manually created by adding rows to the grid. Tip: You can create a binder item with an attachment by dragging and dropping a file from the following programs:
| |
Reference Existing Binder Item |
If a binder item already exists in ProContractor and is shared, you can reference it (rather than creating a new, separate binder item). Click Reference Existing Binder Item, select the binder item you want to reference from a list, and click OK. |
Open |
You can open one or more binder item attachments. You must have the software required to open an attachment—such as Adobe Reader—installed on your computer to be able to view it. Any changes you make to a binder item attachment are saved when you close the attachment. In the Select column, select the checkbox for each binder item you want to include in the e-mail and click Open. |
|
You can send one or more binder items in e-mail message. You must have MAPI-compliant e-mail software—such as Microsoft Outlook—installed on your computer to send an e-mail message with a binder item. In the Select column, select the checkbox for each binder item you want to include in the e-mail and click E-mail. |
Binder grid | |
Select |
Select the checkbox to perform an action on the binder item, such as opening the item's attachment or sending the item in an e-mail. |
Binder Item Type |
Enter the Binder Item Types screen for the binder item or click |
Description |
Enter a description of the binder item. |
Date |
Initially displays the current date. If you want to modify the date for the binder item, enter the new date or click |
Shared |
Select the checkbox to make this binder item available for reference throughout ProContractor. |
Attachment Value |
Enter the full path and file name of the binder item attachment or click |
Attachment Type |
Displays the file type for the attachment. |
Attachment Method |
Defaults to the last attachment method used. Click
|
Attach when E-mailing |
Select the checkbox to have ProContractor include the attachment when sending an e-mail using the On Save of Document E-mail checkbox. This checkbox is always selected for the document's PDF file. |
Status |
Click
|
Owner |
By default, displays the current ProContractor user ID. If needed, enter the Users screen for the binder item owner or click |
Reminder Date |
Enter the date for the reminder for the binder item or click |
Notes |
Enter any comments or notes about the binder item. You can enter formatted text in this field. Click |
Inactive Date |
If the status is Inactive, enter the date the binder item became inactive or click |
Priority |
Click
|
Source Type Grid - When you click When you add a binder item to another source using the Source Type grid, the binder item is automatically shared. Note: You cannot add binder items using the Source Type grid for the following source types: Connect Settings, Meeting Minutes Agenda, Meeting Minutes Action Item, Customer Lien Releases, and Vendor Lien Releases.
| |
Source Type |
Enter the type for the source to which you want to add the binder item or click |
Source Area |
Displays the additional information about the source where relevant. For example, if the source is a vendor invoice, this field would display the company and vendor for the invoice. Source area information is not available for all sources. |
Source |
Enter the code that identifies the source to which you want to add the binder item or click |
Source Name |
Displays the name of the source. |
User-Defined Fields sub-tab - If any user-defined fields exist for this function, this sub-tab appears. You can User-Defined Fields screen to customize this function. Any user-defined fields appear on this sub-tab. Complete the user-defined fields as needed. |