Daily reports

You can use daily reports to track equipment, weather, and the daily activity of the crews on the job site. Certain actions, such as adding daily reports, require a license as well as security permission. Contact your project administrator if you are unable to perform some actions using the mobile app.

Note: Daily reports are not applicable for projects in the free version of ProjectSight.

Daily reports list view

Figure 1. List view

Daily reports list view

  1. Downloads all daily reports
  2. Number of daily reports downloaded
  3. Record status
  4. Approved records are locked and cannot be updated
  5. Date of report
  6. Downloads all the drawings or files linked to this daily report. Any new links will be automatically downloaded when the project is synced.
  7. Total approved labor
  8. Weather condition
  9. Number of notes

Daily report record view

Figure 2. Record view

Daily report record view

  1. Copy from another daily report
  2. Save the record
  3. Date of report
  4. Record status - Approving a daily report does not affect the labor card.
  5. Total lost productivity. Select toggle arrows to change the unit of measurement.

For more information on daily reports, see: